Skip to main content

Template: CEA Technical Standards for Connectivity to the Grid (CTU Tests)

IND flag

Template version: v1

NEW!

Country:

IND flag

IND

Software required:

PSS®E
PSCAD™

Source: CTU | List of studies/tests to be conducted by RE Generators/Parks in process of submission of final technical connection data for demonstrating compliance with CEA technical standards for connectivity to the grid | Rev.0 | 09 March 2025

Preview of template's gridmo Flow showing Nodes

How to add this template to your project

  1. From within your gridmo project, open the flow dropdown and select 'Add flow'.
  2. Select the template you want to use and click 'Add to project'.

screenshot of the gridmo web app adding a flow to a project

Background

Grid connection requirements in India are defined through a combination of regulations issued by the Central Electricity Authority (CEA) and the Central Electricity Regulatory Commission (CERC), primarily via the CEA Technical Standards for Connectivity to the Grid (TSCG) and the Indian Electricity Grid Code (IEGC).

The CEA Technical Standards establish the technical standards for connection to the transmission system, including performance capabilities for renewable energy generators. Renewable generators are required to submit tests and study reports to the Central Transmission Utility (CTU) as part of the connection process.

This template includes the tests specified by CTU to demonstrate compliance with the CEA Technical Standards, in both RMS and EMT platforms. These include the following:

TestRelevant Regulation Clause
Reactive power capability testCEA TSCG: Part-II.B2(1)
Capability to operate in frequency range: 47.5 Hz to 52 HzCEA TSCG: Part-II.B2(2)
Capability to provide rated output in frequency range of 49.5 Hz to 50.5 HzCEA TSCG: Part-II.B2(2)
Low voltage ride throughCEA TSCG: Part-II.B2(3)
Active power setpoint and rate of change of active powerCEA TSCG: Part-II.B2(4)(i)
Frequency response testCEA TSCG: Part-II.B2(4)(ii,iii), IEGC: 30(10)
Demonstration of immediate real power primary frequency responseCEA TSCG: Part-II.B2(4)(ii,iii)
High voltage ride throughCEA TSCG: Part-II.B2(7)

Reference

Common assumptions

  • Power quality tests (such as current harmonics, DC current injection and flicker study) in EMT platform (Section 1, Part 4 of the CTU test document) and not currently part of this template.
  • All tests performed at the SCR and X/R specified by the Global Variables $ind_cea_standards_scr and $ind_cea_standards_xr. By default these are set to SCR=5 and X/R=10, as per Section K of the CTU test document.
  • By default, all Plot Nodes are configured to benchmark PSS®E and PSCAD™ results. This is the recommended approach due to its simplicity. If desired, you can enable the PSCAD™ only and PSS®E only Plot Nodes to submit separate DMAT reports for each software package.

Reactive power capability test

The purpose of this test is to demonstrate the reactive power capability of your generator.

Assumption
  • To demonstrate that your generator meets CEA's V-Q curve criteria, the operating points we have chosen are the corner points of the V-Q capability requirement which corresponds to Qmax and Q=0 MVAr when the voltage at POI = 0.95 pu, as well as Qmin and Q=0 when the voltage at POI = 1.05 pu.
  • The test document specifies the test to be performed at a finite SCR (as specified by the Global Variable $ind_cea_standards_scr). However we recommend performing this test at infinite SCR to prevent your generator from affecting the voltage at POI, thus not giving the exact voltage to satisfy the test criteria. By default, this test has been setup to be performed at infinite SCR.
  • For this test, we have assumed the transformer tap position is not locked (i.e. free to move) during this test.

Capability to operate in frequency range: 47.5 Hz to 52 Hz

The purpose of this test is to demonstrate your generator's ability to operate in the frequency range of 47.5 Hz and 52 Hz.

Assumption
  • A rate of change of frequency (RoCoF) of 4 Hz/s has been chosen when changing the frequency during this test.
  • The test document specifies the generator may initialize at any power factor, hence this template initializes the generator at an initial Q specified by the global variable $project_q_normal_pu, i.e. the typical reactive power when the generating system is at normal operating voltage.
  • The test document specifies the PPC frequency flag to be off for the simulation. We have assumed this is referring to the frequency control functions of the generator, which are configured by the Global Variables $psse_freq_flag_off, $psse_freq_flag_on, $pscad_freq_flag_off and $pscad_freq_flag_on.
  • It is unclear what simulation duration the test should be performed for, hence a simulation duration of 30 seconds has been chosen by default.
  • The test document specifies the test to be performed with '± 5% voltage variation'. As such, this test has been performed at POI voltage = 0.95 pu and 1.05 pu, as well as POI voltage = 1.0 pu.

Capability to provide rated output in frequency range of 49.5 Hz to 50.5 Hz

The purpose of this test is to demonstrate your generator's ability to provide rated output in the frequency range of 49.5 Hz and 50.5 Hz.

Assumption
  • A rate of change of frequency (RoCoF) of 4 Hz/s has been chosen when changing the frequency during this test.
  • The test document specifies the PPC frequency flag to be off for the simulations. We have assumed this is referring to the frequency control functions of the generator, which are configured by the Global Variables $psse_freq_flag_off, psse_freq_flag_on, pscad_freq_flag_off and pscad_freq_flag_on.
  • It is unclear what simulation duration the test should be performed for, hence a simulation duration of 30 seconds has been chosen by default.

Low voltage ride through

The purpose of this test is to demonstrate your generator's low voltage ride through capability.

Assumption
  • The test document does not specify the initial reactive power the generator should initialize at, hence Q is initialized at the typical reactive power when the generating system is at normal operating voltage, specified by the global variable $project_q_normal_pu.

Active power setpoint and rate of change of active power

The purpose of this test is to demonstrate your generator's ability to operate in active power control mode.

Assumption
  • To demonstrate the active power ramp up and ramp down tests, we have chosen a magnitude change of 10% (of the generator's rated active power). Hence, for the ramp up test, the initial dispatch is at 90% which ramps up to 100% of the project rated active power. For the ramp down test, the initial dispatch is 100% and ramps down to 90% of the project rated active power.

Frequency response test

The purpose of this test is to demonstrate your generator's ability to respond to frequency changes.

Assumption
  • A rate of change of frequency (RoCoF) of 4 Hz/s has been chosen when changing the frequency during this test.
  • The frequency change step sizes for this test are: ± 0.01 Hz, ± 0.02 Hz, ± 0.03 Hz, ± 0.05 Hz, ± 0.075 Hz, ± 0.1 Hz, ± 0.125 Hz and ± 0.15 Hz. If required, the frequency change step sizes chosen in this test in the Loop Variable $l_frequency_change can be modified to show insensitivity to the frequency change until the deadband is exceeded.

Demonstration of immediate real power primary frequency response

The purpose of this test is to demonstrate your generator's ability to provide an immediate real power primary frequency response for frequency deviations in excess of 0.3 Hz.

Assumption
  • A rate of change of frequency (RoCoF) of 4 Hz/s has been chosen when changing the frequency during this test.

High voltage ride through

The purpose of this test is to demonstrate your generator's high voltage ride through capability.

Assumption
  • The CTU test document specifies that RMS Test No. 38-40 are to be performed with an initial active power dispatch of 0.2 pu, however the equivalent test in EMT (Test No. 72-74) are specified with an initial active power dispatch of 0.25 pu. We have assumed this is an error in the document, so we have configured the RMS tests with an initial active power dispatch of 0.25 pu to also allow for benchmarking with the EMT simulations.
  • The test document does not specify the initial reactive power the generator should initialize at, hence Q is initialized at the typical reactive power when the generating system is at normal operating voltage, specified by the global variable $project_q_normal_pu.
  • For tests with target voltage 1.1 pu, the test requirement states the duration of the voltage rise must be 'continuous'. For the purpose of simulation, we have sustained the voltage rise for 10 seconds and assumed that is satisfactory to demonstrate the requirement.

Sources

Revision history

Version 1 | 20 April 2026

  • First release.